Golar LNG is set to begin commissioning operations on its second floating LNG production unit as it resolves its dispute with project operator BP and awaits the delayed start-up of a related floating storage production and offloading vessel.
Announcing what it described as a “commercial reset” today, Tor Olav Troim-controlled Golar said all disputes, including the current arbitration process, are now settled, and the parties are realigned towards reaching commercial operations date (COD) for the Greater Tortue Ahmeyim project on the maritime border of Mauritania and Senegal.