Sempra Energy has applied to construct and operate facilities to re-liquefy boil-off gas at its Cameron LNG Gulf Coast import terminal in Louisiana.



The developer has asked the Federal Energy Regulatory Commission for a permit to install a 12 million cubic feet per day liquefaction unit.



Approval is being sought no later than 6 April to allow construction to begin in May and the infrastructure to go into service at the 1.5