Spanish terminal Saggas said this week it has connected up its fourth storage tank, putting the 150,000 cubic-metre unit on track to begin operations in the fourth quarter.



A Saggas source said last week that testing had begun on the 8.76 billion cubic metres per annum terminal’s latest tank, marking the end of major construction works.