- Crews at the GLNG project in Queensland have begun pouring foundations for the train 1 compressor. Operator Santos, which owns a 30% stake in the 7.8 million tonnes per annum development, also reported engineering and procurement for the 420-kilometre feedstock gas pipeline is 80% complete. Contractor Saipem has completed fabrication of 300 kilometres of pipe. Bulk earthworks are 75% complete and construction of storage tank foundations has started.Photo: