Commissioning of the Manzanillo LNG terminal in Mexico is facing fresh delays as LNG carriers still cannot access the facility.



Dredging of the Cuyutlan lagoon and removal of a railway bridge (pictured above) across the harbour have yet to be completed, pushing the first cool-down cargo into next month, according to Mexican media reports.



The commissioning cargo was expected by 1 September but is now due in October.