Petronet LNG should commission its Kochi LNG import terminal in India within two months.

The cool-down process had been slated for December, however, work on the first two phases of the regasification project is 97% complete, a company official told Two Circles.net.

The import facility will have 2.5 million tonnes per annum of first-phase capacity, with expansion work being carried out simultaneously which will quickly lift the total to 5 million tpa.