Excelerate Energy plans a quick-fire construction programme for its Aguirre Offshore GasPort LNG import project in Puerto Rico.
The floating regas specialist hopes to start building the marine infrastructure and subsea interconnecting pipeline for the terminal in October 2013.
The marine facilities will be completed by September 2014 and the pipe will take another month to commission.
Work on the topsides will get under way in February 2014 and also be finished by October.