Singapore LNG is almost halfway through the overall development of the nation’s maiden LNG terminal and physical construction is around 25% complete.



According to the operator, piling for the facility’s third LNG tank has finished.



Work has kicked off on the project’s substation, underground seawater lines and the firewater storage tanks. The terminal is expected to come online in mid-2014 with an initial capacity of 3.5