Cheniere Energy is ahead of schedule at the Sabine Pass liquefaction project and has accelerated the target completion date for trains 1 and 2.The developer said engineering is now 21.1% finished with 18.7% of procurement wrapped up, leaving the entire project 10.5% complete.“The overall project is progressing ahead of the contractual schedule basis,” said Cheniere in an update filed with the US Federal Energy Regulatory Commission.Build