- Mexico’s Comision Federal de Electricidad (CFE) is wrapping up commissioning at the new Manzanillo LNG terminal. The west coast facility should be operational by 1 May, CFE’s Federico Lopez told the CWC America’s Summit. The 500 million cubic feet per day terminal was inaugurated on 30 March.
- Total has sent a commissioning cargo to Jakarta Bay to be transferred to Indonesia’s first floating storage and regasification unit.
Latest Jobs
News briefs
CFE wrapping up commissioning of Manzanillo terminal, while Total sends cool-down cargo to Indonesia's maiden FSRU.
27 April 2012 13:03 GMT
Updated
27 April 2012 13:03 GMT