At least half of the deliveries for the 17 LNG carrier newbuildings set aside for the TotalEnergies-led Mozambique LNG project have been shunted out by another six months.
Several sources following the business closely said the delivery dates on the eight LNG carrier newbuildings being built at Samsung Heavy Industries have been put back to handovers scheduled between March 2026 and March 2027.